Child renewal.
Dates:
- 2021-09-03 Received
- 2021-08-31 Dispatched
- 2021-08-28 Approved
- 2021-08-11 Being processed
- 2021-08-08 Submitted
Times:
- Total 26 days
- “In processing” queue 17 days
- Approved to printed took 4 days (bank holiday)
- TNT/FedEx then took 3 days to deliver it